Uses of Lead Time in Oracle Fusion :
Item level
BPA Level - The lead time defined on the BPA lines are displayed when the user searches and compares items from the catalog.
Min Max -
1. Pre-processing, Processing lead times: they are added to the current date for determining the requisition need by date.
2. Post-Processing lead times: it is added to the Min-max supply cut off date for determining the availability of the supply quantity from the reqs and po supply.
Agreement date is the earliest of these 3 dates: Date when agreemeent was communicated to the supplier, Date when agreement was acknowledged by the supplier, Date when Agreement became live and went under change control.
Item level
BPA Level - The lead time defined on the BPA lines are displayed when the user searches and compares items from the catalog.
Min Max -
1. Pre-processing, Processing lead times: they are added to the current date for determining the requisition need by date.
2. Post-Processing lead times: it is added to the Min-max supply cut off date for determining the availability of the supply quantity from the reqs and po supply.
Agreement date is the earliest of these 3 dates: Date when agreemeent was communicated to the supplier, Date when agreement was acknowledged by the supplier, Date when Agreement became live and went under change control.